Executive Command Center
Aurora Manila Hotel · Manila, Philippines · 350 keys · Opening November 2030
On TrackT-1,513 days
Countdown to grand opening
1,513
days
Grand opening Friday, November 15, 2030
Composite project health99/100
AI executive summary
Updated 8m agoAurora Manila Hotel is trending 14 days behind against the approved opening schedule. The critical path is currently governed by Design Freeze. There are 2 high-impact decisions awaiting executive sign-off and 4 high-severity risks requiring active mitigation. Cost exposure remains within governance tolerance; the operator readiness index is the leading indicator to watch over the next 30 days.
Delivery intelligence
Ask about your portfolio
Answers are drawn only from evidence you are authorised to see, and every material statement is cited. Intelligence can explain and recommend — it never changes a record.
Portfolio context · read-onlySynthetic demonstration data
Delivery intelligence is available to invited, signed-in users. The demonstration walkthrough remains open without signing in.
Are we opening on time?
+14d
Schedule variance
Behind baseline
Is the critical path holding?
+19d slip
Design Freeze
Next gate · 2027-11-20
What decisions are pending?
4
Executive decisions
2 high impact
What's blocking us?
4
High-severity risks
6 active blockers
Are we on budget?
-1.2%
Budget variance
vs. approved GMP
Overall project health
99
Composite score
/100 · weighted index
Countdown to opening
1,513
Days remaining
Grand opening Nov 15, 2030
Workstreams off track
4
Below 25% readiness
People · Sales
This week
Requires executive attention
- 1All-day dining brand vs bespoke conceptRequested by Operator · Due 2027-10-01 · Approvers: Owner Board, Operator VP F&BHigh impactIn Review
- 2Guestroom bathroom material paletteRequested by Interior Designer · Due 2027-08-14 · Approvers: Owner Rep, Operator DesignMedium impactOpen
- 3Spa operator selectionRequested by PMO · Due 2027-12-01 · Approvers: Owner Board, OperatorMedium impactOpen
- 4Sustainability certification targetRequested by Owner · Due 2027-09-05 · Approvers: Owner BoardHigh impactIn Review
Top blockers & risks
- Local authority permit delayP4×I5Owner: PMO · Mitigating
- FF&E lead-time slippageP3×I4Owner: Procurement · Open
- Contractor cash-flow strainP5×I4Owner: Cost Consultant · Open
- GM appointment pendingPeople · Lead: HR Director
- PMS vendor selectionSystems · Lead: IT Lead
Hospitality lifecycle
Stage-gate progression to opening
Stage 1
Concept
100% complete
Stage 2
Design Dev.
62% complete
Stage 3
Tender
18% complete
Stage 4
Construction
6% complete
Stage 5
FF&E / OS&E
0% complete
Stage 6
Pre-Opening
4% complete
Stage 7
Soft Opening
0% complete
Stage 8
Grand Opening
0% complete
Workstream health
Pre-opening readiness indexPeople22%
Next: Executive hires by T-18
Brand40%
Next: Brand launch plan T-12
Systems30%
Next: PMS contract T-15
Sales18%
Next: Sales gallery live T-14
F&B35%
Next: Test kitchen T-9
Rooms25%
Next: SOP library T-12
Engineering20%
Next: Systems handover plan T-10
Safety30%
Next: Crisis drill T-6
Licensing15%
Next: Filing T-9
Upcoming critical gates
- 60%Design FreezeForecast 2027-11-20 · Owner PMO
- 45%Mock-up ApprovalForecast 2028-06-15 · Owner Operator
- 0%Soft OpeningForecast 2030-10-15 · Owner GM
- 0%Grand OpeningForecast 2030-11-15 · Owner Owner