Opening Readiness
Aurora Manila Hotel · Opening Fri Nov 15 2030
T-1572 days
Executive question
Will the hotel be ready to welcome its first guest?
Composite readiness sits at 26%.6 pre-opening streams are carrying live blockers that need executive clearance.
AI InsightSystems (PMS/POS) and Talent hiring are the two streams most likely to compress into the T-3 month window if not accelerated now.
Streams tracked
9
Monitor
Blocked streams
6
Watch
Days to opening
1,572
Critical
Countdown to opening
1,572 days
Overall readiness
26%
People
22%Lead
HR Director
Next milestone
Executive hires by T-18
Blockers
- • GM appointment pending
Brand
40%Lead
Operator Marketing
Next milestone
Brand launch plan T-12
Systems
30%Lead
IT Lead
Next milestone
PMS contract T-15
Blockers
- • PMS vendor selection
Sales
18%Lead
DOSM
Next milestone
Sales gallery live T-14
Blockers
- • Rate strategy pending
F&B
35%Lead
F&B Director
Next milestone
Test kitchen T-9
Blockers
- • Menu concept sign-off
Rooms
25%Lead
Rooms Director
Next milestone
SOP library T-12
Engineering
20%Lead
Chief Engineer
Next milestone
Systems handover plan T-10
Blockers
- • CMMS selection
Safety
30%Lead
Security Lead
Next milestone
Crisis drill T-6
Licensing
15%Lead
Legal
Next milestone
Filing T-9
Blockers
- • Liquor license timeline
T-12 months
- GM appointed
- Executive committee hired
- Pre-opening budget approved
- PMS/POS vendors contracted
T-9 months
- Sales gallery live
- Brand launch plan approved
- F&B menu direction locked
- Licensing filings submitted
T-6 months
- Line staff hiring wave 1
- Systems installation complete
- Uniform vendor confirmed
- Crisis drill scheduled
T-3 months
- Rooms mock-up finalised
- OS&E receiving underway
- Pre-opening PR launch
- TOP inspection preparation