Design Control

Drawing packages, submittals, samples, mock-ups and RFIs through consultant → PMO → operator → owner review.

Executive question
Which design packages are holding up sign-off?
6 packages in circulation. 3 are with reviewers beyond the standard 10-working-day window and risk delaying tender.
AI InsightThe Guestroom Interiors package (Rev C) is the highest-leverage submittal — its approval releases four downstream FF&E procurement scopes.
In review
3
Watch
Approved
1
Healthy
Rejected
0
Act now
PackageTypeDisciplineRevSubmitted byReviewerDueStatusLatest comment
Guestroom Interiors Package Rev C
DP-101
DrawingInteriorsCID ConsultantOperator Design2027-08-14Under ReviewAwaiting operator brand comments
Lobby Lighting Sample Board
DP-102
SampleInteriorsALighting ConsultantPMO2027-07-01ApprovedApproved with note on Kelvin range
Life Safety Strategy Report
DP-103
SubmittalMEPBMEPAHJ2027-09-05IssuedSubmitted for authority review
RFI-088 Ballroom Column Grid
DP-104
RFIStructure-ContractorArchitect2027-07-25Under ReviewStudying alternate grid impact
Guestroom Full Mock-up Inspection
DP-105
Mock-upInteriors1ContractorOperator2027-10-20DraftScheduling inspection with operator
F&B Concept Narrative
DP-106
BriefF&BBF&B ConsultantOwner2027-08-30Under ReviewOwner requesting menu direction