Aurora Manila Hotel · Hotel Project

Manila, Philippines · 350 keys · Current phase: Design Development

On TrackOpening November 2030
Executive question
What single asset am I building — and is every workstream still pulling in the same direction?
350-key upper-upscale hotel in Manila, Philippines, delivered under Design Development discipline for a Q4 2030 opening. Six delivery workstreams are converging toward Design Freeze; operator coordination is the current dominant driver.
AI InsightDevelopment approvals and Operator Coordination are moving at different speeds. A joint alignment session before month-end would de-risk the freeze gate.
Total tasks
18
Overdue
3
Decisions pending
4
RFIs open
7
Budget variance
-1.2%
Days to opening
1572

Workstream progress

Weighted completion across delivery streams.

Development55%
Design62%
Procurement18%
Construction8%
Operator Coordination48%
Pre-Opening6%

Critical path

Items driving the opening date.

  1. 1Design Freeze — target 20 Nov 2027
  2. 2Tender Issue — target 05 Mar 2028
  3. 3Guestroom Mock-up Approval — Jun 2028
  4. 4Main Contract Award — Aug 2028
  5. 5Structural Topping Out — Q3 2029
  6. 6FF&E Installation — Q2 2030
  7. 7Soft Opening — Oct 2030

Recent activity

  • AR
    A. Reyes approved Lobby Lighting Sample Board
    2h ago
  • OD
    Operator Design commented on Guestroom Interiors Rev C
    5h ago
  • MC
    M. Cheng updated status of MEP Schematic Coordination
    yesterday
  • P
    PMO logged decision MEP substation location shift → Approved
    2d ago
  • C
    Contractor raised RFI-088 Ballroom column grid
    3d ago