Aurora Manila Hotel · Hotel Project
Manila, Philippines · 350 keys · Current phase: Design Development
On TrackOpening November 2030
Executive question
What single asset am I building — and is every workstream still pulling in the same direction?
350-key upper-upscale hotel in Manila, Philippines, delivered under Design Development discipline for a Q4 2030 opening. Six delivery workstreams are converging toward Design Freeze; operator coordination is the current dominant driver.
AI InsightDevelopment approvals and Operator Coordination are moving at different speeds. A joint alignment session before month-end would de-risk the freeze gate.
Total tasks
18
Overdue
3
Decisions pending
4
RFIs open
7
Budget variance
-1.2%
Days to opening
1572
Workstream progress
Weighted completion across delivery streams.
Development55%
Design62%
Procurement18%
Construction8%
Operator Coordination48%
Pre-Opening6%
Critical path
Items driving the opening date.
- 1Design Freeze — target 20 Nov 2027
- 2Tender Issue — target 05 Mar 2028
- 3Guestroom Mock-up Approval — Jun 2028
- 4Main Contract Award — Aug 2028
- 5Structural Topping Out — Q3 2029
- 6FF&E Installation — Q2 2030
- 7Soft Opening — Oct 2030
Recent activity
- ARA. Reyes approved Lobby Lighting Sample Board2h ago
- ODOperator Design commented on Guestroom Interiors Rev C5h ago
- MCM. Cheng updated status of MEP Schematic Coordinationyesterday
- PPMO logged decision MEP substation location shift → Approved2d ago
- CContractor raised RFI-088 Ballroom column grid3d ago